Dobson Substation SMS Upgrade

Client

Transpower


Description

Install new Substation Management System (SMS) at Dobson Substation


Value

$120,645


Key Dates

Commenced: 01/11/15
Completed: 17/04/16


Project Details

Remove existing Harris SCADA system and replace with new SMS.


Project Outcomes

Install new SMS panel Install new cooper control modules and associated Data devices in all protection panels Install and terminate new fibre cabling between control units and MFDF cabinet, install associated patch leads Wire up all station alarms through to the SMS cabinet Wire up all transformer and line protection alarms and controls through to the new control units. Test all new alarm and control points through to system SCADA Remove all old SCADA cabling and panels


Performance

All new equipment was installed to a high standard. All new alarms and controls were commissioned through to system SCADA with no issues. Project completed on time